The TAS event approvals guide

Everything an organiser in Tasmania typically needs. Not every item applies — use the checker to get your own list.

Council · start 8 weeks out

Council event application / land booking

Book the venue and lodge an event application with your Tasmanian council for any event on council-managed land.

  • Most Tasmanian councils require an event application 6–12 weeks ahead; major events often 3–6 months.
  • Use of public land, erecting structures or selling goods usually needs a permit under the Local Government Act 1993 (Tas) and council's public land by-law.
  • Some reserves are Crown land managed by the Parks and Wildlife Service and need a separate permit.
  • Expect hire fees, a bond, and a site plan review.

Paperwork: Event application form, Site plan, Run sheet, Certificate of currency

Your organisation · start 4 weeks out

Public liability insurance

Councils typically require $10–20 million public liability cover, noting council as an interested party.

  • Stallholders, food vendors and ride operators should supply their own certificates of currency.
  • Check the exact cover amount required in your council's event terms.

Paperwork: Certificate of currency (organiser + all vendors)

Your organisation · start 6 weeks out

Risk management plan

A written plan identifying hazards, controls, and who is responsible.

  • Cover crowd, weather, fire, lost children, medical, and site hazards.
  • Include an emergency management plan with evacuation points and contacts.
  • Organisers have duties under the Work Health and Safety Act 2012 (Tas).

Paperwork: Risk register, Emergency management plan

Department of State Growth · start 12 weeks out

Road closure & Traffic Management Plan

Closing or affecting roads needs a Traffic Management Plan approved by council and, for state roads, the Department of State Growth.

  • Follow Austroads/AS 1742.3-based traffic management guidance adopted by Tasmanian councils.
  • State roads and highways need Department of State Growth approval in addition to council.
  • Traffic control plans must be prepared by an accredited traffic management person.
  • Notify affected residents, businesses and bus operators ahead of time.

Paperwork: Traffic Management Plan, Traffic Control Plans, Resident notification letter

Tasmania Police · start 8 weeks out

Notify Tasmania Police

Notify your local Tasmania Police district for large gatherings, road events and licensed events.

  • Police input is often required as part of traffic approval and liquor permit processes.
  • Large events may need user-pays police.

Paperwork: Event notification to Tasmania Police

Tasmanian Liquor and Gaming Branch · start 6 weeks out

Special permit (liquor) for the event

Selling or supplying alcohol at a one-off event needs a special permit under the Liquor Licensing Act 1990 (Tas).

  • Apply well ahead of the event — the Liquor and Gaming Branch recommends several weeks' notice.
  • All servers need a current Tasmanian RSA (Responsible Service of Alcohol) certificate.
  • Check whether the site is subject to an alcohol-free area declaration by council.
  • Larger events require an Alcohol Management Plan and police/council consultation.

Paperwork: Special permit application, Alcohol Management Plan, Staff RSA list, Landowner consent

Council · start 4 weeks out

Temporary food stall approvals

Food vendors must register with council under the Food Act 2003 (Tas) and follow temporary event guidelines.

  • Each business needs council registration or notification for temporary food premises.
  • Many vendors need a trained Food Safety Supervisor or equivalent knowledge.
  • Provide hand-washing, waste and grey-water facilities.
  • Gas cylinders and cooking equipment need a fire safety check.

Paperwork: Vendor list, Food stall applications, Food safety training records

Council · start 6 weeks out

Temporary structures (stages, marquees, seating)

Stages, tents and grandstands may need council approval and engineer sign-off.

  • Smaller temporary structures may be exempt under council's building and planning exemptions.
  • Larger marquees, stages and seating usually need a permit or planning approval.
  • Expect to supply structural engineer certification and an installer's compliance statement.
  • Check for underground services before pegging.

Paperwork: Structure specifications, Engineer certificate, Wind/weather management plan

Council · start 6 weeks out

Amplified sound & noise management

Amplified music needs council approval and must stay within noise limits and curfews.

  • Council sets permitted hours and levels under the Environmental Management and Pollution Control Act 1994 (Tas).
  • Notify nearby residents; larger events may need a noise management plan.
  • Playing recorded music publicly needs a OneMusic Australia licence.

Paperwork: Noise management plan, Resident notification, OneMusic licence

Council · start 8 weeks out

Late-night operation

Events running past around 10pm face stricter noise, lighting and security conditions.

  • Most councils require music to stop between 10pm and 11pm in residential areas.
  • Plan lighting, transport home and pack-down noise.

Paperwork: Extended hours request, Lighting plan

WorkSafe Tasmania · start 4 weeks out

Fireworks display

Only a licensed pyrotechnician can run a display, with notice to WorkSafe Tasmania and fire services.

  • The pyrotechnician must hold a current Tasmanian high-hazard explosives licence and lodge notification before the display.
  • Tasmania Fire Service must be notified; displays are cancelled on Total Fire Ban days.
  • Council landowner consent and resident notification are needed.

Paperwork: Pyrotechnician licence, WorkSafe notification, Fireworks plan & exclusion zone

Your organisation · start 6 weeks out

Licensed security & crowd management

Crowd controllers must hold a Tasmanian security licence; councils and police set staffing ratios for large events.

  • A common rule of thumb is 2 guards for the first 100 people, then 1 per additional 100 — confirm with council and police.
  • Include a crowd management plan, entry/exit points and capacity limits.

Paperwork: Security provider licence, Crowd management plan

Your organisation · start 4 weeks out

First aid & medical services

Provide qualified first aid; large events need a medical provider and Ambulance Tasmania notification.

  • Major events should notify Ambulance Tasmania and may need a dedicated medical plan.
  • Plan for heat, shade and drinking water.

Paperwork: First aid provider booking, Medical plan

Council · start 4 weeks out

Toilets, waste & cleaning

Show enough toilets, bins and cleaning for your crowd size.

  • Councils often refer to Building Code ratios for temporary toilets; include accessible units.
  • A waste management plan with recycling streams is commonly required.

Paperwork: Waste management plan, Toilet hire booking

Consumer, Building and Occupational Services (CBOS) Tasmania · start 4 weeks out

Fundraising, raffles & lucky draws

Raising money for a cause may require fundraising registration; raffles follow Tasmanian gaming rules.

  • Charitable fundraising is regulated under the Collections for Charities Act 2001 (Tas) via CBOS.
  • Raffles and lucky draws must follow the Gaming Control Act 1993 (Tas); larger prize pools need a permit.

Paperwork: Fundraising registration, Gaming permit records

Council / Marine and Safety Tasmania · start 8 weeks out

Beach, waterway or foreshore use

Beach and water events need extra approvals and water-safety planning.

  • Water-based activities on navigable waters need approval from Marine and Safety Tasmania (MAST).
  • Engage surf lifesaving or professional lifeguards for swim events.
  • Some foreshores are Crown land or Parks and Wildlife Service reserves needing separate permission.

Paperwork: MAST approval (if on water), Water safety plan

Tasmania Fire Service · start 2 weeks out

Open flames, BBQs & bushfire season

Open fires are restricted during the fire permit period and banned on Total Fire Ban days.

  • A fire permit may be required during the declared fire permit period (generally spring–autumn).
  • Have a fire-weather contingency and extinguishers at each cooking point.

Paperwork: Fire permit (if required), Fire safety checklist

CASA · start 4 weeks out

Drone filming

Flying over crowds needs a CASA-certified operator with the right approvals.

  • Recreational flyers cannot fly over or within 30 m of people.
  • Many councils also require permission to launch from parks.

Paperwork: Operator ReOC/RePL, Drone flight plan

Your organisation · start 4 weeks out

Accessibility & inclusion

Plan accessible paths, parking, toilets and viewing areas.

  • Consider quiet spaces, Auslan interpreters for programmed content, and clear signage.

Paperwork: Accessibility checklist